Which of the following is a key characteristic of at-risk construction management?

Prepare for the CMAA Certified Associate Construction Manager Exam. Study using flashcards and multiple-choice questions, each with hints and explanations. Ensure your success!

Multiple Choice

Which of the following is a key characteristic of at-risk construction management?

Explanation:
In at-risk construction management, the construction manager takes on construction responsibilities and risk, effectively serving as the general contractor during construction. This means the CM is engaged early to assist with design and planning, then delivers the project under a guaranteed maximum price, directly managing construction activities, subcontractors, procurement, and schedule while bearing the risk for cost overruns. This setup differentiates it from roles that are purely design-focused, like a design consultant, or those limited to testing, commissioning, or owner financing and accounting.

In at-risk construction management, the construction manager takes on construction responsibilities and risk, effectively serving as the general contractor during construction. This means the CM is engaged early to assist with design and planning, then delivers the project under a guaranteed maximum price, directly managing construction activities, subcontractors, procurement, and schedule while bearing the risk for cost overruns. This setup differentiates it from roles that are purely design-focused, like a design consultant, or those limited to testing, commissioning, or owner financing and accounting.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy