An SPI of 0.8 means that the project is:

Prepare for the CMAA Certified Associate Construction Manager Exam. Study using flashcards and multiple-choice questions, each with hints and explanations. Ensure your success!

Multiple Choice

An SPI of 0.8 means that the project is:

Explanation:
Schedule Performance Index measures how efficiently the project is progressing against the plan by comparing the value of work actually performed to the value of work planned. It’s calculated as EV divided by PV. If SPI is less than 1, you’re behind schedule; if it’s greater than 1, you’re ahead; if it equals 1, you’re on schedule. An SPI of 0.8 means you’ve earned value equal to 80% of what was planned by this point, so about 20% of the planned progress is missing. That’s why the project is behind schedule by 20%. The other interpretations don’t fit: 50% behind would require an SPI around 0.5, 80% complete isn’t a direct read on schedule efficiency, and ahead of schedule would need an SPI above 1.

Schedule Performance Index measures how efficiently the project is progressing against the plan by comparing the value of work actually performed to the value of work planned. It’s calculated as EV divided by PV. If SPI is less than 1, you’re behind schedule; if it’s greater than 1, you’re ahead; if it equals 1, you’re on schedule. An SPI of 0.8 means you’ve earned value equal to 80% of what was planned by this point, so about 20% of the planned progress is missing. That’s why the project is behind schedule by 20%. The other interpretations don’t fit: 50% behind would require an SPI around 0.5, 80% complete isn’t a direct read on schedule efficiency, and ahead of schedule would need an SPI above 1.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy